The Following Data Is Received From Your Contractor Budgeted Cost Of Work Performed (Bcwp) = $200 Budgeted Cost Of

Question

the following data is received from your contractor budgeted cost of work performed (bcwp) = $200 budgeted cost of

work schedule (bcws) = $300 actual cost of work performed (acwp) = $400 budget at completion (bac) = $800 whuch of the following earned value management (evm) metric can be determined from these data? (DAU ACQ 202)

Percent Scheduled=

Percent Complete=

Percent Spent=